# 2025 release schedule

> Track Lerian's 2025 release cycles with the planned start and end dates for each stage so you can align your delivery and rollouts.

In 2025, our release cycles were:

## First cycle

***

| Stage         | Start Date | End Date |
| :------------ | :--------- | :------- |
| **Weeks 1–6** | April 7    | May 16   |
| **Weeks 7–8** | May 19     | May 30   |

## Second cycle

***

| Stage         | Start Date | End Date |
| :------------ | :--------- | :------- |
| **Weeks 1–6** | June 2     | July 11  |
| **Weeks 7–8** | July 14    | July 25  |

## Third cycle

***

| Stage         | Start Date  | End Date     |
| :------------ | :---------- | :----------- |
| **Weeks 1–6** | July 28     | September 5  |
| **Weeks 7–8** | September 8 | September 19 |

## Fourth cycle

***

| Stage         | Start Date   | End Date    |
| :------------ | :----------- | :---------- |
| **Weeks 1–6** | September 22 | October 31  |
| **Weeks 7–8** | November 3   | November 14 |

## Fifth cycle

***

| Stage         | Start Date  | End Date        |
| :------------ | :---------- | :-------------- |
| **Weeks 1–6** | November 17 | December 26     |
| **Weeks 7–8** | December 29 | January 9, 2026 |