Our release process is structured to ensure stability and predictability. Each release follows a clear roadmap with well-defined stages, from initial planning to stable deployment. Throughout the cycle, the team works on improving both Midaz and the Console, refining existing features, and ensuring comprehensive test coverage for every new addition.
How it works
- Weeks 1–6: Development phase – building new features, making improvements, and refining the platform.
- Weeks 7–8: Stabilization and testing – validating every change with rigorous testing to guarantee reliability.
2025 release schedule
First cycle
Stage | Start Date | End Date |
Weeks 1–6 | April 7 | May 16 |
Weeks 7–8 | May 19 | May 30 |
Second cycle
Stage | Start Date | End Date |
Weeks 1–6 | June 2 | July 11 |
Weeks 7–8 | July 14 | July 25 |
Third cycle
Stage | Start Date | End Date |
Weeks 1–6 | July 28 | September 5 |
Weeks 7–8 | September 8 | September 19 |
Fourth cycle
Stage | Start Date | End Date |
Weeks 1–6 | September 22 | October 31 |
Weeks 7–8 | November 3 | November 14 |
Fifth cycle
Stage | Start Date | End Date |
Weeks 1–6 | November 17 | December 26 |
Weeks 7–8 | December 29 | January 9, 2026 |