Release Cycle

Our release process is structured to ensure stability and predictability. Each release follows a clear roadmap with well-defined stages, from initial planning to stable deployment. Throughout the cycle, the team works on improving both Midaz and the Console, refining existing features, and ensuring comprehensive test coverage for every new addition.

How It Works

Each Release Cycle runs through the following stages:

  • Weeks 1-6: Development phase – building new features, making improvements, and refining the platform.
  • Weeks 7-8: Stabilization and testing – validating every change with rigorous testing to guarantee reliability.

2025 Release Schedule


First Cycle

StageStart DateEnd Date
Weeks 1-6April 7May 16
Weeks 7-8May 19May 30

Second Cycle

StageStart DateEnd Date
Weeks 1-6June 2July 11
Weeks 7-8July 14July 25

Third Cycle

StageStart DateEnd Date
Weeks 1-6July 28September 5
Weeks 7-8September 8September 19

Fourth Cycle

StageStart DateEnd Date
Weeks 1-6September 22October 31
Weeks 7-8November 3November 14

Fifth Cycle

StageStart DateEnd Date
Weeks 1-6November 17December 26
Weeks 7-8December 29January 9, 2026